Writing a weather delay letter to the owner

An outline for a short, factual weather delay letter, with fields to fill in and tips for keeping it clear.

A weather delay letter tells the owner, in writing, that weather has stopped or slowed your work. A short, factual letter is easier to act on than a long one. This guide gives an outline. It is general information, not legal advice, and it cannot replace the notice requirements in your contract.

Check what your contract requires first

Before you write, find out:

  • who must receive the notice, and at what address or email
  • how it must be sent, for example by mail, email or a project portal
  • how soon after the delay begins it must be sent
  • whether a particular form or wording is required
  • whether you must follow up later with more detail

If the contract sets these out, follow them exactly. A good letter sent the wrong way or too late may not do its job.

What a weather delay letter usually covers

  • the project name and number, and the contract it falls under
  • the date of the letter and the dates it covers
  • what happened: the weather you saw at the site on each date
  • where any weather data came from, such as the station name and its distance from the site
  • the work that was affected, and for how long
  • what you know today about the effect on the schedule
  • what you are asking for, if your contract provides for it
  • how to reach you

An outline you can adapt

Replace each item in square brackets with the facts for your project.

[Date]

[Recipient name and address, as your contract directs]

Re: [Project name and number], notice of weather delay

Dear [Name],

This letter notifies you that weather affected work on [project name] on these dates: [dates].

What happened. [A short description of the weather at the site on each date, for example rain that started at about [time] and stopped at about [time].]

Weather data. [Source, station name, its distance from the site, and the values for those dates.] A copy is attached.

Work affected. [The activities that could not go ahead, the crews and equipment on site, and how long work was stopped.]

Effect on the schedule. [What you know now. If it is not yet known, say so and give the date you will send an update.]

Request. [What you are asking for, only if your contract provides for it, and the contract section if you know it.]

Please contact me at [phone and email] with any questions.

Sincerely,
[Name, title, company]

The request is the part where wording matters most. If the amount at stake is large or a dispute is likely, have a construction attorney or claims consultant read the letter before you send it.

Tips for keeping it clear

  • Stick to facts you can support: dates, times, what you saw and what you did.
  • Leave out blame and guesses.
  • Write one letter for each event or period. Do not mix in unrelated issues.
  • Attach support: the weather record, pages from the daily log, and a few dated photos.
  • Keep a copy and proof of delivery, and note the date you sent it in your daily log.
  • Read it as the owner would. Could someone who was not there understand what happened?

Attach the weather record

A WeatheredOut report lists the days that potentially met the rules you entered, names the station and its distance, and shows how each day was counted. The full report can be printed or downloaded as a PDF and attached to a letter. To check a value yourself, NOAA Online Weather Data shows observed daily weather. A WeatheredOut report documents what the weather was. Whether a delay affects your schedule or your price is a question for your contract.

For what to keep alongside the letter, see the guide on documenting weather delays.

Common questions

How long should a weather delay letter be?

Short and factual. Give the dates affected, what the weather was, where the weather data came from, what work was affected and what you are asking for, if your contract provides for it.

What should I attach to a weather delay letter?

The weather record, pages from the daily log and a few dated photos. Keep a copy and proof of delivery.

Should a lawyer read the letter first?

If the amount at stake is large or a dispute is likely, have a construction attorney or claims consultant read the letter before you send it.

Official sources

Public NOAA and National Weather Service pages. They open on other sites, which WeatheredOut does not run.

WeatheredOut is documentation software. It is not legal, engineering or scheduling advice, expert testimony, or a determination of contractual entitlement. Verify results against your contract and official records.