How to calculate weather days
How to count the days in a month that meet your contract’s weather rules, with a worked example and what to do about trace rain and missing readings.
Counting weather days means going through a month one day at a time and asking whether the weather met the rules in your contract. The steps are simple. The details, such as what to do when a reading sits exactly on the threshold, are where counts differ. This guide is general information, not legal advice.
Write down the rules exactly
Copy the wording from your contract instead of working from memory. For each type of weather, note the number and the words around it:
- Rain. “At least 0.10 inch” and “more than 0.10 inch” are different rules.
- Cold and heat. “Below 32°F” and “at or below 32°F” are different rules.
- Wind. Note the speed, and whether the contract means sustained wind or a gust. The National Weather Service explains sustained wind in its glossary.
If your contract gives a number of weather days per month that the schedule already allows, write that down too.
Choose the weather station
Weather is measured at stations, not at your site. Pick the station closest to the job that has a complete record for the month, and note its name and distance. If two people choose different stations, they will get different counts. NOAA keeps these daily station records in a database called GHCN-Daily.
Go through the month one day at a time
For each day, compare the station’s daily reading with each rule. In WeatheredOut, a day potentially qualifies if any rule you turned on is met. Your contract may combine rules differently, for example by requiring two conditions together, so check before you rely on a count.
Watch for the edge cases
- Exactly on the threshold. The words decide. “At least” includes the number and “more than” does not. WeatheredOut counts wind only when it is strictly above your number.
- Trace rain. A trace is an amount too small to measure. WeatheredOut counts trace precipitation as 0.00 inch and flags the day.
- Missing readings. If a station reported no value for a day, the day cannot be counted either way. WeatheredOut lists it as insufficient data.
- Multi-day totals. Sometimes a station reports one total that covers several days. WeatheredOut marks those days as needing review instead of counting them.
A worked example
These numbers are made up to show the method. They are not real observations.
Suppose the rule is that a day counts when precipitation is at least 0.10 inch. A station reports this for seven days:
| Day | Precipitation | Counts? |
|---|---|---|
| Day 1 | 0.00 in | No |
| Day 2 | 0.12 in | Yes |
| Day 3 | 0.10 in | Yes: exactly 0.10 is “at least” 0.10 |
| Day 4 | 0.04 in | No |
| Day 5 | Trace | No: a trace counts as 0.00 |
| Day 6 | 0.35 in | Yes |
| Day 7 | 0.09 in | No |
That is 3 potential qualifying weather days out of 7. If the rule said “more than 0.10 inch”, Day 3 would not count and the total would be 2.
Compare the count with your baseline
If your contract lists a number of weather days per month that the schedule already allows, subtract it from your count. WeatheredOut calls that number the baseline and shows the result as potential days over the baseline, never below zero. With 3 potential qualifying days and a baseline of 5, the result is 0. With 8 days and a baseline of 5, it is 3.
The baseline can be one number you enter, a table with a number for each month, or the average of the same month over the previous 5 or 10 years at the same weather station. If an average is not a whole number, you choose whether a half rounds up, rounds down, or the number is left as it is, because contracts differ.
Whether those days change your schedule or your price is decided by your contract, not by the count. The guide on anticipated adverse weather explains how contracts tend to word the allowance.
Common questions
Does a day with exactly 0.10 inch of rain count?
It depends on the wording of your rule. “At least 0.10 inch” includes 0.10 and “more than 0.10 inch” does not. WeatheredOut follows the comparison you choose for rain and temperature, and counts wind only when it is strictly above your number.
How is trace rain handled?
A trace is an amount too small to measure. WeatheredOut counts trace precipitation as 0.00 inch and flags the day.
What if the weather station has no reading for a day?
The day cannot be counted either way. WeatheredOut lists it as insufficient data instead of guessing.
Official sources
Public NOAA and National Weather Service pages. They open on other sites, which WeatheredOut does not run.
- Global Historical Climatology Network daily (GHCN-Daily)NOAA National Centers for Environmental Information. The NOAA database of daily station observations, including precipitation and daily maximum and minimum temperature.
- NOAA Online Weather Data (NOWData)National Weather Service. Look up observed daily weather for a U.S. location. NWS calls these figures preliminary and subject to revision.
- Glossary: sustained windNational Weather Service. How the National Weather Service defines sustained wind: an average over two minutes.
WeatheredOut is documentation software. It is not legal, engineering or scheduling advice, expert testimony, or a determination of contractual entitlement. Verify results against your contract and official records.